|
Email Updates
|
Tokyo triple
Published: May 25, 2010
Three floating cranes have been used to erect sections of a major bridge being built as part of the Tokyo Bay Highway Project in Japan. Sean Johnstone, Yoshifumi Kodama and Takanori Hata report Construction work is progressing steadily on the second phase of the new highway project that is being built across Tokyo Bay. The link is some 4.6km long and connects the central breakwater and the Wakasu area of the bay. The intention is to reduce traffic congestion on coastal roads around Tokyo Port, as well as improving access for container ships, which continue to increase in number. The Tokyo Bay Bridge forms approximately 2.6km of this section, and is a series of spans being built under the jurisdiction of the Kanto Regional Development Bureau, Ministry of Land, Infrastructure, Transport & Tourism. The main bridge crossing is a steel hybrid structure with truss members and single box girder; it is a total length of 792m and has a main span of 440m and side spans of 160m with a short overhang of the truss at the end of each of the side spans. Including the chord members, the total width of the bridge is 22m and it has an effective width of 18.5m which is composed of a total road width of 15.5m and footway width of 3m. Usually, bridges of this size are designed as suspension or cable-stayed structures with tall main towers, but this was impossible here because of the local conditions, and as a result, a hybrid structure with truss members and a box girder was selected. This bridge is economical and offers a clear shipping envelope. It is also open and scenic. Bridge High-performance Steel is being used for the superstructure. This product, which was recently developed by Nippon Steel, has higher strength and toughness than conventional steel products. It was developed specifically for bridges, with high weldability and cold working ability, and its use enables various advantages to be gained. Firstly, it is possible to reduce the weight of the structure since the high strength steel means less steel is required. As a part of its cold bending ability, the bend radius can be up to seven times greater than the plate thickness, resulting in a higher degree of freedom in design and manufacture. For the Tokyo Bay Bridge, Bridge High-performance Steel is used for most of the truss members. The steel deck has a thickness of 16mm and the steel products used include SM400A, SM490Y, BHS500 (steel with identical yield points is used) and high-strength bolts S10T, F10T. BHS500 accounts for some 50% - approximately 10,300t - of the total weight of steel which is approximately 20,500t. All section joints for the main truss that are welded on-site are Z-shaped. In a conventional structure, the welded sections of flanges and webs are in the same positions. However, fatigue considerations dictated that the welded sections of the main truss should be staggered to create Z-shaped joints. In addition, the borders between flanges and webs are not scalloped, which is also intended to avoid fatigue-related problems. To test the weldability of various types of Z-shaped joints in the yard using the box girder section of full-size truss members, the most severe working environment was recreated in order to verify the validity of welding procedures and to verify conditions in the actual construction. Positive results were observed in nondestructive testing and mechanical testing after trial welding. As for the very difficult welding of lower flanges in a diagonal upward direction, it was confirmed that the work could be performed without problem. The procedures for assembly of bridge elements on land fall into three main categories: the assembly of bent equipment, the assembly of single members of side span truss, and assembly of side span steel deck blocks using floating cranes. Bent equipment was set up in a total 32 locations, 16 for each of the main trusses, and rising to a maximum height of more than 37m. The reaction force per location could exceed 500t. The side span truss member were first transported on a barge to the predetermined unloading area. Depending on the weight of the respective truss members, either the crawler cranes used for ground assembly works or the floating cranes were used to lift the members from the barges. Truss members consist of lower chords, lower supports, vertical members, sway bracing, diagonal members, and middle chords. Each of these was assembled on land using single members. For the on-land assembly, 750t, 500t and 300t crawler cranes were used as the largest member weighed approximately 85t. The total weight of truss members was approximately 3,500t, and the total length was more than 230m. The steel deck sections are made up of the deck itself, the main girder web plates, main girder lower flanges, diaphragms, and transverse ribs. The sections were divided into eight smaller sections and assembled in the factory - each weighed approximately 410t and was 34m long, 20m wide and 3.5m high. These were assembled at the Shikoku plant, each generally being made up of two smaller blocks.
The steel deck sections were transported on a barge from the factory to the assembly yard and a 1,400t floating crane was used to lift the sections on to the truss girders. Ground assembly works first started in May 2008 when the first fabricated members started to reach the assembly yards. There were two assembly yards – one at Ariake which was just 4km from the bridge site, and a second at Futtsu which was 34km from the site. The two large units that had been assembled for the side span were loaded from the assembly yard onto a barge for transportation by three large floating cranes operating in unison. Each unit was 232m long, 24m wide, and 35m high and weighed approximately 7,400t. A 24,000t class steel barge was used to transport these units on the two installation operations which took place in September last year. The loading procedure was a major operation involving the use of Japan’s largest floating crane, the 4,100t Kaisho and the No 50 Yoshida and the Musashi, both of which have a capacity of 3,700t. This was only the fourth time in Japan, and the first time for 15 years, that three floating cranes have been used in a simultaneous lift. On board the barge, the truss girder was supported at eight points, which made it imperative to coordinate the three floating cranes in order to accurately position the unit. A truss girder weighing approximately 6,800t could not have been placed directly on to the barge as its weight would have fractured the hull. Therefore, approximately 9,000t of seawater ballast was pumped into the barge to compensate for the load. The truss was secured to eight pedestals on the barge before transportation to the erection site, so that it would be able to handle back-and-forth swing, up-and-down movement and right-and-left tilting. Once loaded on the barge, the truss girder units were transported to the erection site which was about 4km away. The route involved crossing the Tokyo Bay East Route, so the Japanese coast guard closed the shipping route while the barge was in the area. At the erection site, part of the Tokyo Bay East Route was closed and a navigation exclusion zone was set up around the construction area so that a series of operations could be carried out. Partial closure meant that the shipping route width was reduced from 300m to 190m at minimum. Safety was the top priority during transportation because the barge could not enter the East Route and there were only separation distances to the surrounding banks and bulkheads. Once again, three floating cranes were used simultaneously to lift and erect the large blocks. The erection procedure was basically a reverse version of the loading procedure. The final part of the procedure was to remove the lifting gear from the three floating cranes. For the position control, GPS was used to manage the relative distance of front and back in the floating crane positions. Lift control was performed using each floating crane's lift meter when rolling up and down the units. Based on the lift of the base floating crane, Kaisho, the lift values were reported via radio in a timely manner and the other floating cranes rolled up/down by adjusting the lift. To verify the position of the truss unit being lifted, motion gyro sensors (accelerometers) installed on girders were used to verify the tilt of the side span truss. Height limits were established and the actual heights were controlled based on positioning information from a GPS device installed on the shear stop. In advance of the lift, the unique characteristics of each floating crane was established, through coordination testing. Following placement of the side span truss, erection of the upper truss began, with a 450t crawler crane being brought from the assembly yard by a floating crane and installed on the girders. This crane was used on the side span truss girder bridge to erect single members of the upper truss, weighing about 1,000t. The erection procedure took place at a height of 35m above the girders, some 60m above sea level. As general contractor for the side spans, Kawada was responsible for the detailed design, fabrication, erection engineering, erection works and site supervision. Related articles: |
Calendar
Most read articles
|