The second lot of Prešov’s northern bypass will be carried out by a joint venture led by Vinci Construction through its local subsidiaries, Eurovia SK, Eurovia CS and SMS. Vinci has a 34% stake in the joint venture; the other members are Váhostav - SK and TuCon.

The project will include the construction of 12 bridges, a 2km tunnel and 10.2km of dual two-lane highway. Work is scheduled to start in September and will take about four years to complete.

The contract for the next section of Presov bypass has been awarded to a Vinci-led JV

In 2021, Eurovia CS and Eurovia SK completed construction of the south-west section of the Prešov bypass.

The new section will complete the northern part of the city bypass, reducing traffic congestion and journey times for users.