The bids will now be checked before the city's Municipal Roads Directorate makes a decision on the award of the contract.

All but one of the bids was over the client’s estimate of US$28.6 million.

The bids are:

  • Mosty Lodz - US$32 million
  • Bilfinger Infrastructure - US$28 million
  • Metrostav - US$36 million
  • Strabag – US$31 million


All the companies have said that they will provide a 10-year warranty on steel parts and eight years for reinforced concrete elements.

The 523m-long five-span steel bridge over the Vistula River has been closed since the fire in February.