The bridge has been closed to traffic since one of the cast steel connections between the arch and a cable fractured two weeks ago and the cable fell to the deck. A crack was subsequently found on a second connector.

The temporary support system consists of specially-fabricated saddle frames that will sit on top of the arch. Strand jacks will transfer the deck load, allowing the team to dismantle the hangers and replace both top and bottom forked connectors.