Action taken by creditors in recent days led to Concreate USL going into receivership. The city of Ottawa said that work on the bridge is estimated to be about 60% complete and that the city holds a performance bond of CA$23,024,904 (US$23.25 million), which should ensure the completion of the project.

The local councillor whose ward includes the Strandherd-Armstrong Bridge has said that he will work to ensure that construction remains on track. Steve Desroches said that he has been advised that the east and west foundations are 95% complete, the temporary launching system is at 62%, the fabrication of the deck steel has reached 76%. Fabrication of the arch steel is 100% complete and the stay cables are at 50%.