Massman Construction, Traylor Brothers and IHI submitted a bid of US$452,605,568 for Phase III of the four phase construction project. This was more than 50% higher than the department's estimate of US$299 million. A DOTD engineering committee will review the bid and make a recommendation within 45 days on whether it should be accepted or rejected.