A total of 120t of steelwork has been assembled and the span will be installed by axial launching.

The work is carried out as part of the reconstruction and development of the Moscow Railway Inner Belt. The project bgan in May 2013. Mostotrest 2005, which is part of the SK Most Group, has removed the old Khoroshevskoe Highway reinforced concrete overpass. Crews are putting in place drilled piles for the remaining pier.

The new overpass will have three railway tracks and a total length of 100m. The overpass will have an all-steel continuous girder lower-deck structure for ballasted tracks, installed on the same piers.