The appointment by Ruskin Construction involves Structal-Bridges supplying 110 modified Warren girders, structural bearings and modular expansion joints while Rapid Span will produce the steel towers for the bridge's cable-stayed section.

The order for the steelwork marks progress on the bridge superstructure following a hiatus while extensive redesign had been carried out to address buildability issues. The original designer had resigned and Infinity Engineering Group was appointed by the Deh Cho Bridge Corporation to propose solutions. Infinity developed a redesign option that is compatible with the substructure construction that had already been partially completed.