Phase 1 of the project returned the eastbound lanes to use in October. In Phase 2, the remaining concrete spans were realigned and prefabricated bridge sections were inserted on the westbound side to form two lanes. Phase 3 involves an annually-renewable contract to maintain, repair or replace the temporary bridge panels.

Bids will be opened in spring for a new, three-lane bridge with a higher elevation.