Construction of the new reinforced concrete through-arch bridge is scheduled to begin in early 2011 for completion in late 2012.
The six-span bridge has been designed by Texas Department of Transportation.
Construction will begin off site with the contractor building 12 precast arches - two per span. The original bridge will be removed during summer 2012 and the new deck will be placed, requiring a full closure of up to 150 days.
Project reports
Contract awarded for Fort Worth bridge
Tradeco Infraestructura has been awarded a US$22.7 million contract to rebuild the West Seventh Street Bridge across the Trinity River in Fort Worth in the US state of Texas.