Owner Jacques Cartier & Champlain Bridges Incorporated (JCCBI) and contractor Nouvel Horizon Saint-Laurent GP (NHSL) began with the removal of the main span over the St Lawrence River.

Deconstruction of the old Champlain Bridge

The span, which had been part of the bridge for over 60 years, was detached from the structure in a night-time operation. The 117.5m-long and 2,200t component began its multi-hour descent the next morning. Strand jacks installed on anchor spans on each side enabled it to be lowered 33m onto an assembly of two barges in the middle of the seaway.  

Deconstruction of the old Champlain Bridge

The bridge's replacement opened in 2019 and the approach to removal of the bridge was set out in October 2020, following NHSL's formal appointment in June 2020 (links open in new tabs).

“The dismantling of the steel structure that crowned the original Champlain Bridge for the last 60 years marks a significant milestone in this major deconstruction project,” said Dominic LeBlanc, minister of intergovernmental affairs, infrastructure and communities. “This operation demonstrates JCCBI’s and their partner’s innovation and regard for the environment, as does their recycling program, which will give a second life to the bridge materials. Congratulations to all those involved in this project for the past 18 months. They are executing a major operation with respect for the environment and the residents living nearby.”

Deconstruction of the old Champlain Bridge

Sandra Martel, chief executive officer of JCCBI, said: “The original Champlain Bridge has slowly disappeared from the Montreal landscape over the past 18 months, and today the heart of the bridge has been detached from its structure. The deconstruction process has posed many technical challenges, including the complex and delicate task of lowering the main span. The teams at JCCBI and NHSL have all done excellent work not only at this stage but throughout this major project to minimise the impacts on the public and protect the environment while maintaining high health and safety standards for workers.

NHSL project director Fabrice Guedon said: “Nearly two years of design, coordination and detailed planning have gone into today’s lowering of the main span, which is a unique operation in Canada. Although this type of work is carried out occasionally around the world, it has never been done on this scale in Canada, especially in winter conditions and under the operational constraints of this project. I want to congratulate our teams for their innovative work, which has been directly and indirectly supported by our local and international suppliers and stakeholders.”

Before lowering the main span, work to reinforce the steel structure was done to maintain the integrity of the anchor spans and the long span during the descent. The teams also had to install special-purpose bearings before taking down the span.

Deconstruction of the old Champlain Bridge

The span will be dismantled in the spring.

Deconstruction of the old Champlain Bridge

In the coming months, teams will take apart the cantilever sections that were attached to the main span and dismantle the anchor spans using cranes on the jetties and dike. These sections will be deconstructed chord by chord and then either recycled or reused.

After 18 months of work, the Île des Sœurs abutment, 26 spans, 14 piers and 4 footings have been deconstructed, bringing the deconstruction project to 50% completion, which is in keeping with the original work schedule.